February 23, 2010

Box factory cleanup creeps forward

Turning the former Mills box factory site into a municipal parking lot, a project that attracted the first federal stimulus money to Bristol last spring, is about to take another crucial step toward completion.
Robyn Bugbee, the city’s grants administrator, said the city will hire an expert to create the final remediation plan for the polluted site on School Street in May. It is seeking proposals next month. CLICK HERE FOR STORY

*******
Copyright 2010. All rights reserved.
Contact Steve Collins at scollins@bristolpress.com

September 23, 2009

No delay on box factory cleanup, city says

City leaders said Wednesday they’re not putting off the cleanup of a polluted parcel downtown.
The federal stimulus cash that City Hall plans to tap to help clean up a contaminated former box factory site downtown doesn’t require the work to be done for nearly three more years.
But city officials said Wednesday they expect to be finished long before the deadline.
By springtime, the city should be able to begin to do “the dig and haul” that would remove most of the polluted soil on the School Street parcel, according to Robyn Bugbee, the city’s grants administrator.
Bugbee said that neither the city nor the Environmental Protection Agency has any desire “to sit around” and wait to get the work done.
To meet the federal guidelines governing a $345,000 brownfields grant is that the remediation of the polluted site has to be completed by August 2012.
That doesn’t mean that a proposed municipal parking lot on the site will be finished, however. The lot requires additional funding. There is no set timetable to complete it, officials said.
The Board of Finance backed the project this week on a 7-2 vote – with only Roald Erling and Mark Peterson voting against it – despite some misgivings about the way the economy is heading.
The city aims next to solicit proposals from engineering firms that are capable of overseeing the entire remediation process so that a single licensed environmental professional can handle the entire job, Bugbee said.
By March, she said, the city will have used stimulus cash to hire a firm, conduct activities to involve the community, enroll in a voluntary state remediation program and secure EPA and state Department of Environmental Protection approvals to start the work itself.
The federal government rules require each of those steps be done by next August, she said, a year after the city formally received its grant money. It got official notice only on August 22, months after it heard informally at a press conference held by the EPA on the site.
City officials plan to spend the federal stimulus cash first, then dip into the $268,000 in municipal matching funds required to complete the job that fiscal overseers approved.
The 50 to 75-space parking lot will take extra money that’s not allocated yet.
The remediation effort, though, will involve at least some pavement.
Public Works Director Walter Veselka said that some areas of the site will need to be capped with asphalt to prevent water from reaching the ground beneath, where it could perhaps carry contaminants into the stream that runs through the property.
It’s possible that most of the site will wind up with a layer of pavement, officials said, even before a parking lot is built. It would serve only as a sub-layer for the eventual parking lot, however.
Bugbee said it’s important to get the cleanup underway as early as possible in case the city finds something unexpected when it starts digging out polluted soil.
An early start, she said, ensures there is plenty of time to cope with any unanticipated problems without worrying about the three-year deadline to use the stimulus cash.
The box factory site has been the subject of a number of environmental studies over the past decade that have generally laid out what’s in the ground that needs to be removed.
Bugbee said that “the dirty dirt” there will be scooped out and hauled away in keeping with environmental protocol.
Other sections of the lot will be paved, Veselka said.
The factory itself burned in a spectacular fire about 12 years ago. The city wound up taking the property for back taxes a year later and razing what was left of the buildings on it.
Ultimately, the area is expected to provide parking for the neighboring Board of Education, the Imagine Nation museum across the street and nearby businesses, including Mafale’s Plaza.
Bugbee said some bus parking will be included to help the museum

*******
Copyright 2009. All rights reserved.
Contact Steve Collins at scollins@bristolpress.com

City: No delay on box factory cleanup

City leaders said Wednesday they’re not putting off the cleanup of a polluted parcel downtown.
The federal stimulus cash that City Hall plans to tap to help clean up a contaminated former box factory site downtown don’t require the work to be done for nearly three more years.
But city officials said Wednesday they expect to be finished long before the deadline.
By springtime, the city should be able to begin to do “the dig and haul” that would remove most of the polluted soil on the School Street parcel, according to Robyn Bugbee, the city’s grants administrator.
Bugbee said that neither the city nor the Environmental Protection Agency has any desire “to sit around” and wait to get the work done.
To meet the federal guidelines governing a $345,000 brownfields grant is that the remediation of the polluted site has to be completed by August 2012.
That doesn’t mean that a proposed municipal parking lot on the site will be finished, however. The lot requires additional funding. There is no set timetable to complete it, officials said.

More to come later.

*******
Copyright 2009. All rights reserved.
Contact Steve Collins at scollins@bristolpress.com

Box factory cleanup backed but lagging

Note: If you're interested in this story, please check the blog later today for a more detailed -- and accurate -- account of the project's timeline and the city's plans.

The first federal stimulus cash to come to Bristol – to help clean up the former H.J. Mills box factory site – has yet to create a single job.
And officials are no hurry to get a shovel ready to finish work on it.
The bulk of the cleanup project won’t take place until at least springtime – partly to ensure the city has enough money in its coffers to pay its share of the tab – and a planned parking lot on the property may not happen for years.
The $613,000 project to clean up the polluted School Street parcel – where a municipal parking may someday be built – isn’t completely on hold, however.
The Board of Finance backed the project Tuesday on a 7-2 vote – with only Roald Erling and Mark Peterson opposing it – despite some misgivings.
The city’s grants administrator, Robyn Bugbee, said the city can hire an engineering firm to come up with the detailed plans needed, seek ways to get the public more involved and line up the required state and federal approvals.
By the time all of that is done, the finance board could take another look in March and decide whether Bristol can afford the $268,000 in municipal funds required to match the $345,000 the federal Environmental Protection Agency is handing over from the stimulus package.
While it’s likely the city will move ahead with the cleanup in the spring, it’s less clear the parking lot will be constructed soon. The lot would have between 50 and 75 spaces.
That could wait “a year or two” if the economy remains poor, Finance Chairman Rich Miecznikowski said.
The finance chief said the city will have “a better idea what kind of costs we have” by springtime and can decide then what it needs to do to cope.
Erling, vice chairman of the nine-member finance board, said that given the need to make sure pollution doesn’t leach into the stream that cuts through the property, he figures costs will rise after engineers take a hard look at the project.
U.S. Sen. Joe Lieberman joined an array of local, state and federal officials at the site last May to announce the brownfields funding that would help with the cleanup.
“There couldn’t be a better economic stimulus project than these brownfields grants,” said Lieberman.
But one of the aims of the stimulus program – to get shovels in the ground and put people to work – hasn’t happened on the School Street site so far.
On the other hand, Lieberman said cleanups are a good “long-term investment in economic growth,” which may still prove true.
The site has been blighted for more than two decades. Following a major fire a decade ago that destroyed the factory building, the property has been a weed-filled eyesore owned by the city.
After announcing the funding last spring, Lieberman said he loves to see the results of government investment.
“I can’t wait to come back to Bristol,” to see the finished project, Lieberman said during his visit.
He may have to wait awhile.

*******
Copyright 2009. All rights reserved.
Contact Steve Collins at scollins@bristolpress.com